Planning the next phase

plan/ is only for planning the next big piece of work, before it starts. It is empty of plans while the current board is clean.

Where other things live:

What Where
Work tracking and checkboxes ../TODO.md (tick boxes only there)
Current design and decisions ../ARCHITECTURE.md
Long-form docs ../docs/
Records of finished workstreams ../docs/workstreams/

Proposing a phase plan

  1. Copy TEMPLATE.md to plan/<short-name>.md (for example plan/phase-5-alerting.md).
  2. Fill in:
    • Goal: what changes for users or operators, in a few sentences.
    • Scope: what is in, and explicitly what is out.
    • Workstreams: independent tracks with owned files, dependencies and done criteria, so they can run in parallel without merge conflicts.
    • Open decisions: questions that need a human call, each with options and a recommendation.
    • Exit criteria: how you will know the phase is done (commands to run, behaviour to demonstrate).
  3. Review and settle the open decisions in the plan file.
  4. When the plan is accepted, move the work into ../TODO.md: add the phase milestone and one checklist per workstream with stable task IDs. Fold the accepted decisions into the Decisions section of ../ARCHITECTURE.md.
  5. When the phase finishes, move the plan file (and any per-workstream notes) to docs/workstreams/ as an archived record and collapse its tasks in TODO.md into the Completed table.